Applying for partial approval for the construction and operation of an installation
Service description
Due to their nature or operation, parts of installations may cause harmful effects on the environment or otherwise endanger, significantly disadvantage or disturb the general public or the neighborhood.
If you want to set up or operate an installation, you need a partial permit from the competent authority. A partial permit can be applied for and issued if the full permit for a requested installation has not yet been granted, but the following requirements are met:
- There is a legitimate interest in the granting of a partial permit,
- the approval requirements for the subject of the partial approval applied for have been met and
- a preliminary assessment shows that there are no insurmountable obstacles from the outset to the construction and operation of the entire installation with regard to the licensing requirements.
Prerequisites
- The sub-project fulfills the requirements of the Federal Immission Control Act.
- The sub-project does not conflict with any other public law regulations or occupational health and safety concerns.
- A preliminary assessment has shown that there are no insurmountable obstacles to the construction and operation of the entire plant from the outset with regard to approval.
- The preliminary overall assessment is no longer binding if the factual or legal situation or individual inspections change within the scope of subsequent partial approvals and the assessment also changes as a result. In this case, the authority may refuse the approval or further partial approvals.
What documents are required?
- Drawings, plans, expert opinions
- Explanations
Please contact the responsible office for further required documents.
What fees apply?
The amount of the fee is variable and usually depends largely on the installation costs.
What deadlines do I have to observe?
You must apply for approval before you start the project.
Legal basis
- § Section 8 of the Act on Protection against Harmful Environmental Impacts from Air Pollution, Noise, Vibrations and Similar Processes (Federal Immission Control Act - BImSchG)
- § Section 10 (5), sentence 1 of the Act on Protection against Harmful Environmental Impacts from Air Pollution, Noise, Vibrations and Similar Processes (Federal Immission Control Act - BImSchG)
Legal remedy
- Appeal. Further information on how to lodge an objection can be found in the notification.
- Lawsuit
Short text
- Partial approval for the construction of an installation Issue
- Permit for the construction and operation of part of an installation
- Approval is granted after preliminary assessment by the competent authority
- Responsible: the authority responsible for you
Author
Forwarding service: Deep link to the source portal Forwarding service: Deep link to the source portal- Applying for partial approval for the construction and operation of an installation in Rhineland-Palatinate
Display of performance in the source portal
- Applying for partial approval for the construction and operation of an installation
Display of performance in the source portal
- Applying for partial approval for the construction and operation of an installation in Rhineland-Palatinate
Typing
2Library entry status
6Catalog entry status
6